News

Nov 10, 2025 News

2025 Faith and Aging Conference Was a Success!

On Friday, The Bethany Group's annual Faith and Aging Conference took place at the Days Inn Norsemen in Camrose! Thank you to everyone who attended, to our hosts and to our keynote speakers Dr. Robyne Hanley-Dafoe and Jessica Holmes. It was a wonderful day!… Read more
Dec 05, 2022 News

Melodie Stol Earns Queen's Platinum Jubilee Medal

The Bethany Group's own Melodie Stol (Stakeholder Relations Advisor) was honoured in Calgary, AB on December 3rd when she earned the Queen's Platinum Jubilee Medal. Stol was the first female Mayor of Blackfalds, serving for ten years, from 2007 to 2017.… Read more
Nov 01, 2022 News

Centennial Celebration for The Bethany Group

On Saturday, October 22nd, The Bethany Group was proud to celebrate the milestone achievement of 100 years in operation. Tucked in the atrium and auditorium of our Heritage Building, with historical posters, decorations, and many people who have made a… Read more

Construction Update

Posted on May 18, 2018


Construction on the Rosehaven Atrium will begin on May 23rd with the scaffolding being installed.

The Atrium project will include the removal of the existing skylights and the construction of a new sloped roof system. The new roof will be enclosed but with new tubular daylighting devices that will ensure the space is still bright and airy. As well, new lighting will be installed in several areas throughout the Atrium to help brighten the space.

We will be doing everything possible to ensure activities and programming will not be impacted too much by working with several departments and the contractors.

The first part of the working schedule for the project will be:

May 23 - June 8

Scaffold installed in phases:

  • Cafeteria seating Area 1
  • Staff lounge patio Area 2
  • Woodworking area Area 3

Wed. May 23 

  • Area 1 - Cafeteria furniture cleared from scaffold area by end of day
  • Vending machines relocated to alternate locations

Thur. May 24

  • Contractor orientation pre-start
  • Scaffold layout delivery and installation
  • Delivery at main floor entrance doors would require 1 hr
  • Core samples perimeter atrium

Fri. May 25 

  • Scaffold lower section install

Mon. May 28

  • Working at upper floor level Scaffold upper section install

Tues. May 29

  • Install beams, dust barrier and work deck

Wed. May 30 

  • Install, dust barrier and work deck

Thurs. May 31

  • Complete work deck, column protection

Fri. June 1

  • Area 2 scaffold install lower section
  • Atrium Roof protection Plan

Mon. June 4

  • Area 3 scaffold install lower section
  • Atrium Roof protection plan

Tues. June 5

  • Area 2 scaffold install upper section
  • Atrium area 1 exterior wall demo
  • New Pony wall
  • Wall protection              

Wed. June 6

  • Area 3 scaffold install upper section
  • Atrium area 1 exterior wall /roof demo
  • Membrane roof seal
  • Pony walls
  • Wall protection

Thurs. June 7

  • Area 2/3 Install beams, dust barrier and work deck
  • Atrium area 1 exterior wall demo
  • Membrane roof seal

Fri. June 8

  • Complete work deck, column protection
  • Atrium area 1 exterior wall /roof demo
  • Membrane roof seal 
  • Wall protection